1.5.3 MAST SET-UP INSTRUCTIONS
!
MAINTAIN SAFE MINIMUM APPROACH
DISTANCES
FROM
READ THE SAFETY PRECAUTIONS
!
BEFORE RAISING THE MAST, CHECK
THAT
NO
OBSTRUCTIONS
LOCATED ABOVE THE MAST TO A
HEIGHT OF 10 METRES.
Fig 1.5.7
1. Ensure all four outrigger arms are
extended and the jack leg feet are in
firm contact with the ground. Adjust
height of each jack leg to level the
lighting tower using the bubble-level.
2. Open the control panel access door
Start the engine /generator and allow it
to complete its run-up sequence.
3. To raise mast to the required height,
press the enable button and at same
time, toggle the mast raise/lower
switch 'up'.
1001281353
Oshkosh Corporation Classification ‐ Restricted 
MACHINE OPERATION
JLG LT
POWER
LINES.
ARE
JLG Industries (Australia) Pty Ltd
Oshkosh Corporation
3
4. To rotate a lighthead with electro-
mechanical drive, press the enable
button and toggle the rotate switch.
5. Finally, to adjust the lighthead tilt angle,
press the enable button and toggle the
tilt control switch.
!
TO AVOID CRUSHING INJURIES, KEEP
HANDS AND LIMBS WELL CLEAR OF
MOVING
MAST
AND
CRUSHING HAZARDS.
Fig 1.5.8
1.5.4
TURNING LIGHTS ON
The lighting tower's control module is
factory pre-set with two machine stop/start
modes.
1) Manual Start/Stop
2) Auto Start/Stop
A summary of each control mode follows.