Optional Equipment (Field Installed); Floor Stands - Trane CyberAir DX Installation, Operation And Maintenance Manual

Perimeter precision air conditioners 21-105 kw / 60 hz
Table of Contents

Advertisement

Installation
Figure 14. Down-flow Configuration Air Patterns
TOP FREE RETURN
Optional Equipment (Field
Installed)
Note: Do not mount any optional equipment on the unit
access doors.

Floor Stands

Install the optional floor stand directly on the sub-floor,
ensuring the side with the "FRONT" label is facing the
same direction as the front of the precision A/C unit. Refer
to the floor stand assembly drawing for the dimensions
required to cut the raised floor. The floor stand is designed
with adjustable legs, allowing for leveling and overall
height adjustment. Refer to the floor stand assembly
drawing for minimum and maximum height adjustments.
Adjust the height of the floor stand as described in the
sections that follow. Once it is level and even with the
raised floor, lock all the feet in place. Place the A/C unit on
top of the stand.
Floor Stand Height Adjustment
Standard and Low Seismic Floor Stands:
20
RETURN
AIR INLET
SUPPLY
AIR OUTLET
RETURN
AIR INLET
DUCT
TOP DUCTED RETURN
Standard Floor Stands- First loosen the middle hex nut
(jam nut) on each leg. Turn the top hex nut to raise or lower
the floor stand. Lock the height by tightening the middle
hex nut up against the top hex nut.
Figure 15. Standard Floor Stand
"FRONT" LABEL
Low Seismic Floor Stands- First loosen the top hex nut
(jam nut) on each leg. Turn the entire foot weldment to
raise or lower the floor stand. Lock the height in place by
tightening the top hex nut up against the fixed hex nut in
the floor stand leg.
SUPPLY
AIR OUTLET
FLOOR STAND LEG
THREADED ROD
TOP HEX NUT
MIDDLE HEX NUT (JAM NUT)
BOTTOM HEX NUT (FIXED)
ISOLATION PAD
SS-SVX002B-EN