Location And Fixing; Installation Clearance - Emerson KHZ506 User Manual

Table of Contents

Advertisement

Location and Fixing

• The unit should always be installed in a location that ensures clean air flow. Both service access and
airflow have been considered in making these recommendations.
• Where multiple units are to be installed in the same location, the contractor needs to
consider each individual case carefully.
• Ideally, the unit should be mounted on a solid concrete slab with anti-vibration pads between unit
feet and concrete.
• Ensure that there is no obstruction to air flow into or out of the unit. Remove obstacles which
block air intake or discharge
• The location must be well ventilated, so the air can pass properly through condenser by
maintaining the proper condensation in the system.

Installation Clearance:

It is recommended to have a clearance of 500 mm between the condenser face and adjacent wall or
unit, while a clearance of 500mm on remaining 3 sides and top for service and free circulation.
500
All Dimensions are in mm
Above instructions are recommended for Dual Fan CDU Units Also.