Piping requirements
1. Copper pipes should not be flattened or bended
2. The refrigerant piping should not block the square hole on rack's vertical post, otherwise, it will affect the
installation of customer IT equipment
3. Regarding top piping, see the following figure: 3.27 to avoid impact on IT device installation. The copper pipes
should be routed near the rear left PDU plate and as close to the outside as possible. Make sure the copper
pipes route in the red box area in the figure: 3.27 shown below.
Figure 3 .27
The side view of the top piping area for 8.1kW split cooling