Chapter 1
Getting Started Guide

Install the Switch

OL-9340-01
Before you install the switch, review the Regulatory Compliance and Safety
Information for the Catalyst Express 500 Switch document that came with your
switch.
When selecting an installation site, observe these guidelines:
Cabling is away from sources of electrical noise, such as radios, power lines,
and fluorescent lighting fixtures.
Clearance to the switch front and rear panels is such that
Airflow around the switch and through the vents is unrestricted.
Front-panel LEDs can be easily read.
Access to ports is sufficient for unrestricted cabling.
AC power cord can reach from the AC power outlet to the connector on
the switch rear panel. The power outlet must be accessible at all time
because it serves as the main method to disconnect power from the
switch.
Temperature does not exceed 113°F (45°C), humidity does not exceed
85 percent, and altitude at the installation site is not greater than 10,000 feet
(3049 m).