PLACING THE UNIT
Placing the Unit
Tools and Instruments- Pincers, Wrenches, Facilities to transport and place the unit.
Transportation- Transport the unit as close to the final installation location as practical before unpacking
is performed. Keep the unit upright. When transporting the unit after unpacking has been performed, take
note of the following.
Rolling - Place three equal-sized rollers under the base frames. Each roller must carry both of the outer
frames, and must be situated to balance the unit (refer to the weight balance Fig. 3-1 and Fig.3-2.).
Lifting by Forklift - Insert the forks under the base frames and lift the unit, exercising care to catch both
of the outer frames.
Rigging - Apply spreader bars to the top of the unit, in order to prevent damage to the unit due to cable
scratches.
Fig. 5. Lifting and Rigging
Unpacking - Follow the instructions marked on the packing.
NOTE:
Keep the unit covered with a vinyl cover during installation work for peripheral equipment.