Commissioning; About - Hitachi RWM-2R1E Installation & Operation Manual

And yutaki cascade controller
Hide thumbs Also See for RWM-2R1E:
Table of Contents

Advertisement

UNIT CONTROLLER

7.13.7 Commissioning

Under the commissioning menu it is possible to adjust the several parameters:
Screed Drying:
Circuit 1 setting temperature
Circuit 2 setting temperature
Start screed drying
Pump down procedure:
Duration
Start pump down

7.13.8 About

In this section of the LCD controller it is possible to find the following information:
Contact information:
It is possible and recommendable
to fill this information providing a
contact phone to the user.
105
PMML0575 rev.1 - 09/2021
Air purge procedure:
Duration
Start air purge
Unit test run:
• Duration
• Mode (not available for heating only)
• Start test run
System information:
Unit type
Unit capacity
Serial number
Controller firmware
Indoor PCB firmware
Language package
Refrigerant

Advertisement

Table of Contents
loading

Table of Contents