www.ti.com
3
Electrical Specifications
PARAMETER
Connector J1
JTAG
Connector J3
PMBus connector
Connector J4
UART
Connector J5
JTAG
Connector J38
J38-4
J38-3
J38-2
J38-1
Operation Environment
Operating temperature range
Mechanical Characteristics
Dimensions
Firmware for Testing
Filename
SLUUA80 – January 2013
Submit Documentation Feedback
Table 1. UCD3138OL40EVM-032 Specifications
CONDITION
Standard JTAG communication connection
Port of connection to USB-to-GPIO, pin definition refer
to TI standard USB-to-GPIO document SLLU093
Female DB-9, RS232
Standard JTAG communication connection
Port to use 3.3 V on board to bias external circuit
External 5.0 V to board
External 3.3 V to board
Digital ground DGND
Natural convection
Width
Length
Component height
PWR032_UART0.x0
PWR032_Test_2.x0
Copyright © 2013, Texas Instruments Incorporated
Electrical Specifications
MIN
TYP
MAX
Standard
Standard
Standard
Standard
3.25
3.30
3.45
4.90
5.00
5.10
3.27
3.30
3.33
25
4.0
6.0
0.5
Using the UCD3138OL40EVM-032
UNITS
VDC
°C
inches
3
Need help?
Do you have a question about the UCD3138OL40EVM-032 and is the answer not in the manual?