Quooker COMBI Installation Manual
Hide thumbs Also See for COMBI:

Advertisement

Quick Links

Installation Guide COMBI
Before installing read this guide first

Advertisement

Table of Contents
loading

Summary of Contents for Quooker COMBI

  • Page 1 Installation Guide COMBI Before installing read this guide first...
  • Page 2 If the entire content is used in one go the heating time is ca. 15 min (COMBI 3.0) to 20 min (COMBI 2.2). The Quooker COMBI supplies warm water by mixing boiling water from the Quooker tank with cold water from the water mains inside the mixing valve.
  • Page 3: Technical Specifications

    Declaration of conformity Peteri BV, Staalstraat 13, 2984 AJ Ridderkerk (the Netherlands) herewith declares, on our own responsibility, that the products Quooker COMBI 2.2 and COMBI 3.0 are in accordance with the conditions of the following directives: - 72/23/EEC Low Voltage Directive...
  • Page 4: Content Of The Pack

    Content of the pack 1. Quooker COMBI tank 2. Quooker tap 3. Quooker warm water hose 4. Quooker inlet combination 5. Quooker drill bit, fibre rings, PVC nipple and drain hose 6. Mixing valve - Quooker-brochure - Installation guide and tips for use...
  • Page 5 Overview of Quooker COMBI installation It is recommended that you install the Quooker COMBI in the following order: A. Drill hole B. Fit tap C. Fit inlet combination and mixing valve D. Connect drain E. Connect tank N.B. Bear in mind that the tank, the inlet combination, the mixing valve and the...
  • Page 6 1 Drilling hole Allowing for the basin and mixer tap, select a suitable location for the Quooker tap (see examples). Using the correct drill bit, drill a hole of 32-35 mm in the sink.
  • Page 7: Tightening Screws

    Fitting tap • N.B. The total length of the boiling water hose is only 50 cm. The tank must therefore be fitted close to the tap. An extension hose is available but is not normally required. 1 Tap through sink Push the tap through the hole in the sink.
  • Page 8: Connecting Water

    Connecting water • N.B. The Quooker operates under water supply pressure and must always be fitted with the inlet combination (supplied). • The Quooker boiling water tap must be connected according to the locally applicable regulations. • The pressure relief valve on the inlet combination must be regularly lifted to prevent blocking due to lime scale.
  • Page 9 Connecting drain The Quooker tank releases expansion water through the inlet combination during heating, this water being fed into the grey funnel. The funnel can easily be connected to the drain by means of the drain hose supplied. The drilling kit also supplied can be used to make a connection to the drain pipe.
  • Page 10 Connecting tank • N.B. Do not switch on the Quooker until the tank is filled with water. • The Quooker tank is supplied with a 3-core mains cord with earthed plug. • The Quooker tap is fitted with an indicator lamp which indicates whether or not the heating element is heating.
  • Page 11 ‘Q button on top of the cover and remove the plug from the socket. 2 Allow to drain Open the Quooker tap and do not close it until the water is cold. 3 Isolating Close the main water valve or the stop valve of the inlet combination.
  • Page 12 Q U O O K E R U K L T D Telephone + 44 (0)207 9233355 Fax +44 (0)207 9001590 Internet www.quooker.co.uk E-mail info@quooker.co.uk...

Table of Contents