987MB: Installation, Start-up, Operating and Service and Maintenance Instructions
!
In the State of Massachusetts:
1. Gas supply connections MUST be performed by a licensed
plumber or gas fitter.
2. When flexible connectors are used, the maximum length shall not
exceed 36 in. (915 mm).
3. When lever handle type manual equipment shutoff valves are
used, they shall be T-handle valves.
4. The use of copper tubing for gas piping is NOT approved by the
State of Massachusetts.
Gas piping must be installed in accordance with national and local
codes. Refer to current edition of NFGC in the U.S.A. Refer to current
edition of NSCNGPIC in Canada.
Installations must be made in accordance with all authorities having
jurisdiction. If possible, the gas supply line should be a separate line
running directly from meter to furnace.
NOTE: Use a back-up wrench on the inlet of the gas valve when
connecting the gas line to the gas valve.
The gas supply pressure shall be within the maximum and minimum
inlet supply pressures marked on the rating plate with the furnace
burners ON and OFF.
Gas entry can be from left or right side, or top panel. See
Fig.
31.
Gas Pipe Grommet Required
For Direct Vent Applications
Fig. 29 – Gas Entry
Fig. 30 – Alternate Gas and Electric Entry
NOTE: Top plate may be field drilled for alternate gas and 115 VAC
electric entry.
Refer to
Table 8
for recommended gas pipe sizing. Risers must be used
to connect to furnace and to meter. Support all gas piping with
appropriate straps, hangers, etc. Use a minimum of one hanger every 6
ft. (2 M). Joint compound (pipe dope) should be applied sparingly and
only to male threads of joints. Pipe dope must be resistant to the action
of propane gas.
Manufacturer reserves the right to change, at any time, specifications and designs without notice and without obligations.
NOTICE
Fig. 29
Left Side Gas Entry. Gas Pipe
Grommet Required For Direct
Vent Applications.
1 1/2 inch for Gas
7/8 inch for 115 VAC Electric
Table 8 – Maximum Capacity of Pipe
NOMINAL
IRON PIPE
SIZE
10 (3.0)
IN. (MM)
175
1/2 (13)
3/4 (19)
360
1 (25)
680
1400
1-1/4 (32)
2100
1-1/2 (39)
* Cubic ft of gas per hr for gas pressures of 0.5 psig (14-In. W.C.) or less and a pressure drop
of 0.5-In. W.C. (based on a 0.60 specific gravity gas). Ref:
current edition NFPA54/ANSI Z223.1.
Gas Pressure
Maximum
Minimum
When a flexible connector is used, black pipe shall be installed at the
furnace gas control valve and extend a minimum of 2-in. (51 mm)
outside the furnace.
For direct vent (2-pipe) applications, seal the gas pipe knockout to
prevent air leakage.
Remove the required knockout. Install the grommet in the knockout.
Then insert the gas pipe. The grommet is included in the loose parts bag.
Piping should be pressure and leak tested in accordance with the current
addition of the NFGC in the United States, local, and national plumbing
and
and gas codes before the furnace has been connected.
Refer to current edition of NSCNGPIC in Canada. After all connections
have been made, purge lines and check for leakage at furnace prior to
operating furnace.
PRESSURE TESTING ABOVE ½ psig:
The furnace and it's individual shut-off valve must be disconnected from
the gas supply piping system during any pressure testing of that system
at test pressures in excess of ½ psig (3.5 kPa).
PRESSURE TESTING BELOW ½ psig:
The furnace must be isolated from the gas supply piping by closing its
individual manual shut-off valve during any pressure testing of the gas
supply piping system at test pressures equal to or less than ½ psig (3.5
kPa).
A11338A
FIRE OR EXPLOSION HAZARD
A failure to follow this warning could result in personal injury, death,
and/or property damage.
If local codes allow the use of a flexible gas appliance connector,
always use a new listed connector. Do not use a connector which has
previously served another gas appliance. Black iron pipe shall be
installed at the furnace gas control valve and extend a minimum of 2-in.
(51 mm) outside the furnace.
A170125
An accessible manual equipment shutoff valve MUST be installed
external to furnace casing and within 6 ft. (2 M) of furnace.
Install a sediment trap externally in the riser leading to furnace as shown
in
Fig.
31. Connect a capped nipple into lower end of tee. Capped nipple
should extend below level of furnace gas controls. Place a ground joint
union between furnace gas control valve and exterior manual equipment
gas shutoff valve.
25
LENGTH OF PIPE - FT (M)
20 (6.0)
30 (9.1)
40 (12.1)
120
97
82
250
200
170
465
375
320
950
770
660
1460
1180
990
Table 8
above and 6.2 of the
Natural (in W.C.)
Propane (in W.C.)
13.8
4.5"
WARNING
!
50 (15.2)
73
151
285
580
900
12"