Commissioning The Inverter - SMA SUNNY BOY 3800TL-US Installation Manual

Hide thumbs Also See for SUNNY BOY 3800TL-US:
Table of Contents

Advertisement

SMA America, LLC

7.2 Commissioning the Inverter

Requirements:
☐ AC overcurrent protection and AC disconnecting unit must be correctly designed.
☐ The inverter must be correctly mounted and closed.
☐ The DC Disconnect must be correctly mounted and closed.
☐ All cables must be correctly connected.
1. Place the lower enclosure lid with the 6 screws onto
the enclosure and tighten them using an Allen key
(AF 3) in the order 1 to 6 (torque: 18 in-lbs. (2.0 Nm).
2. Switch on or close all AC disconnecting switches and circuit breakers in the output circuit of the
inverter.
3. If an external DC disconnecting switch is available, switch on or close the DC disconnecting
switch.
4. Turn the rotary switch of the DC Disconnect to the On position.
☑ The inverter carries out an arc-fault circuit interrupter (AFCI) self test.
☑ The green LED is lit and the display shows the device type, the firmware version, the device
names, the country data set and display language. If communication is via Speedwire, then the
status and the versions of the communication assemblies will also be displayed also after the
device names.
The inverter feeds into the grid.
✖ Green LED flashing?
Possible cause of error: The DC input voltage is still too low, or the inverter is monitoring the
utility grid.
• Once the DC input voltage is sufficiently high, the inverter goes into operation.
✖ The red LED is lit and an error message and event number appear in the display?
• Eliminate the error (see Section 11 "Troubleshooting", page 59).
✖ The blue LED is glowing or flashing?
• Eliminate the communication error (see Section 9.3 "LED Signals", page 54).
Installation Manual
7  Commissioning
SB3-5TLUS22-IA-en-16
51

Advertisement

Table of Contents
loading

Table of Contents