Verify that all components are correctly installed, tagged, and without damage.
Mark any checked items with a green marker in the circuit diagram.
4. Check and retighten the compressor cables. Tightening torque: 10 Nm.
5. Check conductor protection circuit.
6. Verify the correct phase sequence of the electrical supply.
7. Check the power supply voltage, and compare to the measured values marked in
the Pre-commissioning certificate.
8. Switch on the power.
9. Check the DC supply voltage.
10. Check the cooling fans and filters in the control cabinet. Check the variable
frequency drives' fans and filters (if present). Start the cooling fans by lowering the
cabinet's internal temperature setpoint. Note down the original setting and reset
after testing.
11. Check that the communication interface is connected and correctly set up.
Refer to the instructions and settings in the Modbus communication list.
12. Check the settings of any overcurrent protective devices.

4.7 First start-up

Set the language, time, and time zone.
Tap the right arrow to continue.