Siemens SIMOTICS S-1FK2 Operating Instructions Manual page 87

Hide thumbs Also See for SIMOTICS S-1FK2:
Table of Contents

Advertisement

Table 7-3
Has the motor been connected so that it rotates in the specified direction?
Have the minimum insulation resistance values been maintained?
Have the grounding and equipotential bonding connections been correctly established?
Is the specified limit speed n
Table 7-4
Has it been ensured that speeds higher than the maximum speed n
Have all supplementary motor monitoring devices been correctly connected and are they
working properly?
Table 7-5
Natural cooling
Have you adapted the torque and power of the motor to the ambient conditions?
You will find information on the derating in the configuration manual.
Observe the information provided in the converter operating instructions.
Table 7-6
Is the brake open when the operating voltage is applied?
Does the brake open and close correctly?
SIMOTICS S-1FK2 synchronous motors for SINAMICS S120
Operating Instructions, 02/2022, A5E46089564B AD
Checklist (3) - checks regarding the electrical system
maintained during the operation on the converter?
max
Checklist (4) - Monitoring equipment checks
Checklist (5) - Cooling system checks
Checklist (6) - Checks regarding the optional brake
Check
Check
max
Check
Check
Commissioning
7.2 Checklists for commissioning
cannot be reached?
OK
OK
OK
OK
85