ESP Platinum QUE
Split Ducted Unit - 3 Phase
Installation and Commissioning Guide - Outdoor
Model Numbers
CRQ2-16AT
CRQ3-18AT
CRQ5-21AT
CRQ5-24AT
IMPORTANT NOTE:
Please read this manual carefully before installing or operating your air conditioning unit.

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the ESP Platinum QUE and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for ActronAir ESP Platinum QUE

  • Page 1 ESP Platinum QUE Split Ducted Unit - 3 Phase Installation and Commissioning Guide - Outdoor Model Numbers CRQ2-16AT CRQ3-18AT CRQ5-21AT CRQ5-24AT IMPORTANT NOTE: Please read this manual carefully before installing or operating your air conditioning unit.
  • Page 2: Table Of Contents

    14. Troubleshooting Guide .......................... 33 15. Fault and Status Codes ........................... 35 16. Frequently Asked Questions ........................36 17. Key Components Parts List ........................38 Installation & Commissioning Guide - ESP Platinum QUE Split Ducted Units Doc. No.0525-063 Ver. 1 190131...
  • Page 3: Inspections

    Check your air conditioning unit and all items against the invoice upon receiving your shipment. Inspect the unit, components and accessories for any sign of damage. If there is any damage to the unit, contact ActronAir Customer Care Department immediately on: 1300 522 722 to obtain a Goods Return Number.
  • Page 4: Safety Instructions

    Blue Hydrophillic coil fins provide protection to your heat exchangers and enhanced heat transfer with increased performance efficiency. System Flexibility The ActronAir Platinum-series of air conditioning units is the first choice for residential, office, schools and other air conditioning facilities applications, both for new construction or retrofitting projects. Refrigerant Handling and Accountability ActronAir strongly urges that all service technicians make every effort possible to reduce the emission of refrigerants to the atmosphere.
  • Page 5: Installation Information

    Take extra care to maintain all service equipment directly supporting refrigerant service work such as gauges, hoses, vacuum pumps and recycling equipment. ActronAir is constantly seeking ways to improve the design of its products, therefore specifications are subject to change without notice. Copyright © 2019 Actron Engineering Pty. Ltd.
  • Page 6 ● Secure the power cords and control cables that goes in/out the unit. Use the cable ties provided in the control box. IMPORTANT NOTES TO INSTALLER This outdoor unit is designed to match only with specific ActronAir indoor unit as specified in the Technical Selection Catalogue. This unit is designed for use with R410A refrigerant only.
  • Page 7: Components Overview

    CIRCUIT BREAKER TERMINAL BLOCKS OUTDOOR UNIT CONTROL BOARD EARTHING BOLTS WITH WASHERS & NUTS ActronAir is constantly seeking ways to improve the design of its products, therefore specifications are subject to change without notice. Copyright © 2019 Actron Engineering Pty. Ltd.
  • Page 8: Outdoor Unit Dimensions / Clearances

    • Do not scale drawing. • MTG C-C DIST = Mounting Center to Center Distance UNIT CORNER WEIGHTS (kg) UNIT MODEL WEIGHT NUMBER (kg) CRQ2-16AT CRQ3-18AT Installation & Commissioning Guide - ESP Platinum QUE Split Ducted Units Doc. No.0525-063 Ver. 1 190131...
  • Page 9 • Do not scale drawing. UNIT CORNER WEIGHTS (kg) UNIT MODE WEIGHT NUMBER (kg) CRQ5-21AT CRQ5-24AT ActronAir is constantly seeking ways to improve the design of its products, therefore specifications are subject to change without notice. Copyright © 2019 Actron Engineering Pty. Ltd.
  • Page 10: Minimum Service Access Areas And Airflow Clearances

    • Under all circumstances, condenser air must not recirculate back onto condenser coil. Keep all clearances free of any obstructions. • Minimum service access areas & spaces for airflow clearances are responsibilities of the installer, ActronAir will not be held liable for any extra charges incurred due to lack of access and space for airflow.
  • Page 11 *Clearances will vary depending on model, see clearance table dimension on Section 06.02. ActronAir is constantly seeking ways to improve the design of its products, therefore specifications are subject to change without notice. Copyright © 2019 Actron Engineering Pty. Ltd.
  • Page 12: Unit Lifting Procedure

    4. SPREADER BAR must be used when lifting the unit. Ensure that the spreader bar is slightly larger than the base. 5. Test lift the unit to determine exact unit balance and stability before hoisting it to the installation location. Installation & Commissioning Guide - ESP Platinum QUE Split Ducted Units Doc. No.0525-063 Ver. 1 190131...
  • Page 13: Fork Lift Method

    Length of fork lift tines must pass the unit middle section, in order to safely carry the unit. ActronAir is constantly seeking ways to improve the design of its products, therefore specifications are subject to change without notice. Copyright © 2019 Actron Engineering Pty. Ltd.
  • Page 14: Outdoor Unit Preparation

    • There is an earth cable attached to the access panel. This must be disconnected first to fully remove the access panel. • You must re-connect the earth cable when re-assembling the access panel. Installation & Commissioning Guide - ESP Platinum QUE Split Ducted Units Doc. No.0525-063 Ver. 1 190131...
  • Page 15: Field Pipe Connection

    0.32 25.5 (1”) 0.52 0.78 0.24 0.36 28.6 (1-1/8”) 0.55 0.83 0.27 0.41 ActronAir is constantly seeking ways to improve the design of its products, therefore specifications are subject to change without notice. Copyright © 2019 Actron Engineering Pty. Ltd.
  • Page 16 2 x 450 mm Spigots DIGITAL SCROLL COMPRESSOR ActronAir is constantly seeking ways to improve the design of it’s products, therefore specifi cations are subject to change without notice, Please check prior to purchase. SRD175C-0100 / SRD175E-0100 -P1- 090326 CAUTION...
  • Page 17 18.30 with Drain Kit COOLING INPUT POWER (kW) ^^ 6.07 ActronAir is constantly seeking ways to improve the design of its products, therefore specifications are subject to change without notice. ction HEATING INPUT POWER (kW) ^^ 5.44 Copyright © 2019 Actron Engineering Pty. Ltd.
  • Page 18: Pressure Testing

    • Oxygen (air) reacts with the compressor oil and can lead to faults such as compressor failure. See Diagram Below: INDOOR UNIT BRAZE JOINTS OPEN HOSE NITROGEN HOSE DETAIL A Installation & Commissioning Guide - ESP Platinum QUE Split Ducted Units Doc. No.0525-063 Ver. 1 190131...
  • Page 19: Evacuation Procedure (Triple Evacuation)

    5. Break the vacuum with dry Nitrogen to 100kPa 6. Release Nitrogen pressure. Evacuate to 500 microns. 7. Open valve ActronAir is constantly seeking ways to improve the design of its products, therefore specifications are subject to change without notice. Copyright © 2019 Actron Engineering Pty. Ltd.
  • Page 20: Electrical Installation

    UPDATED WIRING DIAGRAM IS PROVIDED WITH THE UNIT Outdoor Unit: Located at the back of electrical/compressor acess panel. Indoor Unit: Located at the back of electrical box cover. Installation & Commissioning Guide - ESP Platinum QUE Split Ducted Units Doc. No.0525-063 Ver. 1 190131...
  • Page 21 * DO NOT USE the 2 Core Orange Shielded Data Cable (AEDC1) used on previous ActronAir units. ActronAir is constantly seeking ways to improve the design of its products, therefore specifications are subject to change without notice. Copyright © 2019 Actron Engineering Pty. Ltd.
  • Page 22: Wiring Connection, Control Cable Length And Specification

    CAUTION MEPS C E R T I F I E D LIVE ELECTRICAL WIRING R-410A AUTHORISED TECHNICIANS ONLY INTERNAL CONTROL ISOLATOR FITTED Installation & Commissioning Guide - ESP Platinum QUE Split Ducted Units Doc. No.0525-063 Ver. 1 190131...
  • Page 23: Aedc2 Data Cable Shielding Instructions

    (Refer to unit wiring diagram for complete wiring connection details). OUTDOOR BOARD OUTDOOR BOARD TERMINAL PLUG Fig. 3 ActronAir is constantly seeking ways to improve the design of its products, therefore specifications are subject to change without notice. Copyright © 2019 Actron Engineering Pty. Ltd.
  • Page 24: Demand Response Management

    DRM 3/COMP DRM 2/FAN DRM 1/HEAT DEMAND RESPONSE DEMAND ENABLING DEVICE (DRED) RESPONSE AS4755 COMPLIANT MANAGEMENT DEVICE (OPTIONAL) DEMAND RESPONSE ENABLING DEVICE CIRCUIT DIAGRAM Installation & Commissioning Guide - ESP Platinum QUE Split Ducted Units Doc. No.0525-063 Ver. 1 190131...
  • Page 25: Run And Fault Indication Output

    Additional Refrigerant per 100* charge - (g/m) * For liquid field pipe of 1/2” ActronAir is constantly seeking ways to improve the design of its products, therefore specifications are subject to change without notice. Copyright © 2019 Actron Engineering Pty. Ltd.
  • Page 26 SUCTION charging SCHRADER VALVE DISCHARGE SCHRADER VALVE R410A * REFRIGERANT CONTAINER * Use weighing scale when adding or removing refrigerant charge. Installation & Commissioning Guide - ESP Platinum QUE Split Ducted Units Doc. No.0525-063 Ver. 1 190131...
  • Page 27 17 ±1 2 ±1 CRQ5-24AT 1100 4 ±1 3 ±1 13 ±1 4 ±1 ActronAir is constantly seeking ways to improve the design of its products, therefore specifications are subject to change without notice. Copyright © 2019 Actron Engineering Pty. Ltd.
  • Page 28 130.4 649.8 1782.6 3880.5 140.3 674.3 1831.6 3965.9 150.5 699.4 1881.5 4052.8 161.1 724.9 1932.3 4140.9 171.9 751.3 1984.1 4230.6 183.3 778.3 2036.9 4321.5 Installation & Commissioning Guide - ESP Platinum QUE Split Ducted Units Doc. No.0525-063 Ver. 1 190131...
  • Page 29: Maintenance

    To clean the refrigerant coils, use a soft brush and water spray, such as garden hose or pressure washer with low pressure nozzle. ActronAir is constantly seeking ways to improve the design of its products, therefore specifications are subject to change without notice. Copyright © 2019 Actron Engineering Pty. Ltd.
  • Page 30: Maintenance Frequency Checklist

    Tighten Terminals as necessary on Visual Inspection  Boards printed circuit boards Check all electrical Electrical terminals, mains, Re-tighten if loose.  Connections communications, etc Installation & Commissioning Guide - ESP Platinum QUE Split Ducted Units Doc. No.0525-063 Ver. 1 190131...
  • Page 31 *Service period for filter cleaning may vary depending on operating time & surrounding environment ActronAir is constantly seeking ways to improve the design of its products, therefore specifications are subject to change without notice. Copyright © 2019 Actron Engineering Pty. Ltd.
  • Page 32 / cut out of pressure controls controls, sensors, etc Check for any previous fault Investigate any causes for previous Faults Faults  history on unit. faults, reset fault history. Installation & Commissioning Guide - ESP Platinum QUE Split Ducted Units Doc. No.0525-063 Ver. 1 190131...
  • Page 33: Troubleshooting Guide

    Auto Fan Mode. increases the total fan speed. This will boost fan capacity. ActronAir is constantly seeking ways to improve the design of its products, therefore specifications are subject to change without notice. Copyright © 2019 Actron Engineering Pty. Ltd.
  • Page 34 Check the drain is not piped into the Re-pipe drain with a P-Trap and connect into sewerage drain line. household drainage or storm water drain. Installation & Commissioning Guide - ESP Platinum QUE Split Ducted Units Doc. No.0525-063 Ver. 1 190131...
  • Page 35: Fault And Status Codes

    - Tech Menu (E72) Precharge Relay Open - Tech Menu (E74) Compressor Phase Over Current ActronAir is constantly seeking ways to improve the design of its products, therefore specifications are subject to change without notice. Copyright © 2019 Actron Engineering Pty. Ltd.
  • Page 36: Frequently Asked Questions

    Q. Can you turn the system ON from the zone controller? A. YES. From zone controller, press and hold the power button (approx. 3 sec onds). It will activate the zone and will maintain Installation & Commissioning Guide - ESP Platinum QUE Split Ducted Units Doc. No.0525-063 Ver. 1 190131...
  • Page 37 Q. Does the Que Platinum system use a different zone barrel to the standard ON/OFF type 24volt ActronAir barrels? A. No, they are the same barrels. ActronAir designed these zone motors with the intension to communicate with the Que system.
  • Page 38: Key Components Parts List

    • Nominal airflow is the air supplied by the air conditioners at its standard rating conditions. This data can be found in the ActronAir technical catalogue or by contacting technical support on 1800 119 229 & quoting the applicable unit model 17.
  • Page 39 EEV Stator Coil 4550-031 Reversing Valve 4560-112 Suction Accumulator 4510-026 Crankcase Heater 2025-009 ActronAir is constantly seeking ways to improve the design of its products, therefore specifications are subject to change without notice. Copyright © 2019 Actron Engineering Pty. Ltd.
  • Page 40 Refrigerant Trading Authorisation No.: AU06394 ©Copyright 2019 Actron Engineering Pty Limited ABN 34 002767240. ®Registered Trade Marks of Actron Engineering Pty Limited. Document: 0525-063 Issue Date: 01/2019...

This manual is also suitable for:

Crq2-16atCrq3-18atCrq5-21atCrq5-24at

Table of Contents