Installation; Moving And Storage; Rigging; General - Carrier 40RM007-034 Installation, Start-Up And Service Instructions Manual

Packaged air-handling units 50/60 hz
Table of Contents

Advertisement

Moving and Storage —
storage site, use a fork truck. Do not stack units more than
2 high during storage. If unit is to be stored for more than
2 weeks before installation, choose a level, dry storage site free
from vibration. Do not remove plastic wrap or skid from unit
until final installation.
Rigging —
All 40RM Series units can be rigged by using
the shipping skid. Units are shipped fully assembled. Do not
remove shipping skids or protective covering until unit is ready
for final placement; damage to bottom panels can result. Use
slings and spreader bars as applicable to lift unit.

INSTALLATION

1
General —
Allow 2
/
ft at front and side of unit for service
2
clearance and airflow. For units equipped with an economizer,
refer to the accessory installation instructions for additional
clearance requirements. Be sure floor, wall, or ceiling can
To transfer unit from truck to
support unit weight (Tables 1A-1F). See Fig. 1A-1C for
dimensions.
Uncrating —
Move unit as near as possible to final loca-
tion before removing shipping skid.
Remove metal banding, top skid, and plastic wrap. Examine
unit for shipping damage. If shipping damage is evident, file
claim with transportation agency. Remove base skid just prior
to actual installation.
Check nameplate information against available power
supply and model number description in Fig. 2.
NOTE: Be sure to remove the styrofoam shipping pad from
the thermostatic expansion valve (TXV). Verify that it has
been removed. See Fig. 3.
Accessories —
Refer to instructions shipped with each
accessory for specific information.
2

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents