Page 1
F i x G r i d E a s t - W e s t (short side clamping) F i x G r i d + E a s t - W e s t (long side clamping) INSTALLATION MANUAL...
Page 2
T h e sy stem is to be installed only with ballasting in acc ordance with static loads. You will re ceive these with the planning of your solar plant fro m the Schletter c onfigurator Risk of breakage! PV modules can be damaged if they are stepped on.
Page 3
U s e the current mounting instructions! A c c essible on our website: www.schletter-group.c om in the FixGrid18 section. FIXGRID EAST-WEST I V1 I INSTALLATION MANUAL I 12-2020 SCHLETTER NA Inc. I SUBJECT TO CHANGE WITHOUT NOTICE...
Page 4
T h e mounting times can be optimized by pre-assembling a series of base rails next to each other on mounting fra m e s with the module supports. FIXGRID EAST-WEST I V1 I INSTALLATION MANUAL I 12-2020 SCHLETTER NA Inc. I SUBJECT TO CHANGE...
Page 5
T h e mounting times can be optimized by pre-assembling a series of base rails next to each other on mounting fra m e s with the module supports. FIXGRID EAST-WEST I V1 I INSTALLATION MANUAL I 12-2020 SCHLETTER NA Inc. I SUBJECT TO CHANGE...
Page 6
A n additional surface protection mat should be positioned under joints of the base rails! • If the roof water drains off transversely, an almost unhindered drainage is possible. alway s c entered below bearing FIXGRID EAST-WEST I V1 I INSTALLATION MANUAL I 12-2020 SCHLETTER NA Inc. I SUBJECT TO CHANGE WITHOUT NOTICE...
Page 7
• Secure splice in place using self drilling screws provided, 1 per base rail per splice. FIXGRID EAST-WEST I V1 I INSTALLATION MANUAL I 12-2020 SCHLETTER NA Inc. I SUBJECT TO CHANGE WITHOUT NOTICE...
Page 8
• Connec t the module cable acc ording to the plan. • Repeat steps up to the last module in the row. FIXGRID EAST-WEST I V1 I INSTALLATION MANUAL I 12-2020 SCHLETTER NA Inc. I SUBJECT TO CHANGE WITHOUT NOTICE...
Page 9
Ballasting fro m the c ombination of the 3 possibilities T h e information about ballasting can be obtained with the planning of your solar plant fro m the Schletter c onfigurator. Use fixing flaps to attach the parts of the surface protection mat to the additional trough.
Page 10
At the last ballast tray, the end has to be unfolded again. Further Information about our sys te m s can be found on our website: www.schletter-group.c om in the solar section under D ownloads. FIXGRID EAST-WEST I V1 I INSTALLATION MANUAL I 12-2020 SCHLETTER NA Inc.
Page 11
(PER ONE OF THE TWO MODULES OF THE EAST -WEST CONFIGURATION) BALLAST EXAMPLES FIXGRID 10 (PER ONE OF THE TWO MODULES OF THE EAST -WEST CONFIGURATION) FIXGRID EAST-WEST I V1 I INSTALLATION MANUAL I 12-2020 SCHLETTER NA Inc. I SUBJECT TO CHANGE WITHOUT NOTICE...
Page 12
(PER ONE OF THE TWO MODULES OF THE EAST -WEST CONFIGURATION) BALLAST EXAMPLES FIXGRID 10 + (PER ONE OF THE TWO MODULES OF THE EAST -WEST CONFIGURATION) FIXGRID EAST-WEST I V1 I INSTALLATION MANUAL I 12-2020 SCHLETTER NA Inc. I SUBJECT TO CHANGE WITHOUT NOTICE...
Page 13
BALLAST EXAMPLES FIXGRID 5 + (PER TWO MODULES OF THE EAST-WEST CONFIGURATION) BALLAST EXAMPLES FIXGRID 10 + (PER TWO MODULES OF THE EAST-WEST CONFIGURATION) FIXGRID EAST-WEST I V1 I INSTALLATION MANUAL I 12-2020 SCHLETTER NA Inc. I SUBJECT TO CHANGE WITHOUT NOTICE...
Page 14
C O M P O N E N T S RE COM M ENDED BY S C H L E T T E R F O R E QU I P O T E N T I A L B O ND I NG FIXGRID EAST-WEST I V1 I INSTALLATION MANUAL I 12-2020 SCHLETTER NA Inc.
Page 15
I n s t a l l a ti o n s, C a n a d i an E l e c t r i cal C o d e , P a r t 1 . FIXGRID EAST-WEST I V1 I INSTALLATION MANUAL I 12-2020 SCHLETTER NA Inc.
Page 16
2.Apply a liberal amount of c onductor on front and back side of module fra m e at mounting hole. Although not required, Schletter strongly re co m m e nd the use of conductor c ompound between the mounting surface s in order to better protect the c onnection in all environmental c onditions and pro m o te c onnection longevity.
Page 17
L oosen or re m ove top portion of groundinglog and insert grounding wire into appropriate groove. Gauge of Grounding Wire conductor FIXGRID EAST-WEST I V1 I INSTALLATION MANUAL I 12-2020 SCHLETTER NA Inc. I SUBJECT TO CHANGE WITHOUT NOTICE...
Page 18
WAR N I N G ! T h e PV S ystem m u s t be shut dow n first if it needs any electrical maintenance. Improper maintenance m ay cause lethal electric shocks/ or burns. FIXGRID EAST-WEST I V1 I INSTALLATION MANUAL I 12-2020 SCHLETTER NA Inc. I SUBJECT TO CHANGE...
Page 19
F I X Z- P R O F ILE S I N C L . T U R N - I N C O N N E C T O R Maximum permissible pressure values 5 4 0 0 kPa Maximum permissible tensile values 2 4 0 0 kPa FIXGRID EAST-WEST I V1 I INSTALLATION MANUAL I 12-2020 SCHLETTER NA Inc. I SUBJECT TO CHANGE WITHOUT NOTICE...
Page 20
Q.PEAK DUO‐G5 B.LINE PRO L G4.1 B.LINE PLUS L G4.2 B.LINE PRO L G4.2 B.LINE PLUS BFR G4.1 B.LINE PRO BFR G4.1 FIXGRID EAST-WEST I V1 I INSTALLATION MANUAL I 12-2020 SCHLETTER NA Inc. I SUBJECT TO CHANGE WITHOUT NOTICE...
Page 21
Q.PEAK DUO‐G6+ Q.PEAK DUO‐G6+/SC Q.PEAK DUO‐G7 Q.PEAK DUO‐G8 Q.PEAK DUO‐G8+ Q.PLUS DUO L-G5 Q.PLUS DUO L-G5.1 Q.PLUS DUO L-G5.2 Q.PLUS DUO L-G5.3 B10B68:B138 FIXGRID EAST-WEST I V1 I INSTALLATION MANUAL I 12-2020 SCHLETTER NA Inc. I SUBJECT TO CHANGE WITHOUT NOTICE...
Page 22
LGxxxS1C‐G4 LGxxxS1W‐G4 LGxxxS2W‐A5 LGxxxN2T‐A5 LGxxxN1T‐V5 LGxxxN2T‐V5 LGxxxQ1C‐V5 LGxxxQ1K‐V5 LGxxxA1C‐V5 LGxxxN2T‐J5 LGxxxN1C‐V5 LGxxxN1K‐V5 LGxxxN1C‐N5 LGxxxN1C‐A6 LGxxxN1K‐L5 LGxxxN1K‐A6 LGxxxQ1C‐A6 LGxxxQ1K‐A6 LGxxxN2W‐L5 LGxxxN2W‐E6 LGxxxN2T‐E6 LGxxxN2T‐L5 FIXGRID EAST-WEST I V1 I INSTALLATION MANUAL I 12-2020 SCHLETTER NA Inc. I SUBJECT TO CHANGE WITHOUT NOTICE...
Page 23
STPxxxS – A60U/Wfhb STPxxxS ‐ A72U/Vfh STPxxxS ‐ A72U/Vnh STPxxxS‐24/Vfw FIXGRID EAST-WEST I I400338 I V3 I INSTALLATION GUIDE I 12 - 2020 SCHLETTER NA Inc. I SUBJECT TO CHANGE WITHOUT NOTICE FIXGRID EAST-WEST I V1 I INSTALLATION MANUAL I 12-2020 SCHLETTER NA Inc.
Page 24
TSM‐DEG15MC.20(II) TSM‐DEG18MC.20(II) TSM‐PE06H TSM‐PE15H TSM‐PEG06H TSM‐PEG15H.20 Glacier Series G3 WattPower WP-xxxM/G3-60H-V (325|330|335|340PC) YL260P|255P|250P|245P|240P-29b Yingli G reen Energy YL275P|270P|265P|260P|255P|250P-29b YL290D|285D|280D|275D|270D-30b YL300C|295C|290C|285C|280C|275C-30b YL325P|320P|315P|310P|305P|300P-35b YL340D|335D|330D|325D|320D|315D-36b FIXGRID EAST-WEST I V1 I INSTALLATION MANUAL I 12-2020 SCHLETTER NA Inc. I SUBJECT TO CHANGE WITHOUT NOTICE...
Page 25
ZNShine ZXM6‐60‐xxx_M ZXM6‐H120‐xxx_M ZXM6‐H144‐xxx_M ZXM6‐HLD120‐xxx_M ZXM6‐HLD144‐xxx_M ZXM6‐HLDD144‐xxx_M ZXM6‐LD60‐xxx_M ZXM6‐LD72‐xxx_M ZXM6‐LDD72‐xxx_M ZXM6‐NH120‐xxx_M ZXM6‐NH144‐xxx_M ZXM6‐NHLD120‐xxx_M ZXM6‐NHLD144‐xxx_M ZXM6‐NHLDD120‐xxx_M ZXM6‐NHLDD144‐xxx_M ZXP6‐72‐xxx_P ZXP6‐H144‐xxx_P ZXP6‐HLD120‐xxx_P ZXP6‐HLD144‐xxx_P ZXP6‐LD72‐xxx_P FIXGRID EAST-WEST I V1 I INSTALLATION MANUAL I 12-2020 SCHLETTER NA Inc. I SUBJECT TO CHANGE WITHOUT NOTICE...
Page 26
SCHLETTER NA INC. 5200 77 Center Drive Suite 250 Charlotte, NC 28217 Phone: +1 704 595-4200 Fax:+1 704 595-5210 CANADA: Phone: +1 519 946-3800 rooftopNA@schletter-group.com www.schletter-group.com...