The two steel cables shall be adjusted to
certain uniform tension to ensure the two
carriages are moving synchronously.

10.2.7 Install the power unit and hydraulic lines

Use two M10 Bolt s and washers to fix the power unit
(as shown in Fig. 14a 、14b). for TLT235SC、
TLT240SC 、 TLT235SC ( U ) models, install the
hydraulic line as shown in Fig. 14a , for TLT235SB、
TLT240SB models, , install the hydraulic line as
shown in Fig. 14b and tighten all the fittings to
TLT235、TLT240 Economical Two-post User's Manual
Short screw end, double
nuts tightened
Long screw end,
adjustable
Steel cable
Fig.13b
prevent oil leakage.
Fill the reservoir with hydraulic oil (oil capacity of 10L).
Operate carefully to avoid dust and other pollutants
mixed with the hydraulic oil.
Note
Clean the impurities in the hydraulic line
and remove the protective plug from the
hydraulic cylinder.
When the hydraulic hose installation needs
to go through the column, ensure the
hydraulic hose won't touch any movable
parts inside the column