Check lists after completing the installation

f After completing the installation, you must check the following.
X
Indoor unit
Installation
Outdoor unit
Refrigerant pipe work
Installing the drain pipe
Wiring work
Option
PAC_아프리카 중동향AP80S0A_IBIM_34514A-02_EN.indd 51
• Have you checked the external surface and the internal part of the indoor unit?
• Is the place well-ventilated and ensures space for service?
• Have you checked if the center of the indoor unit is ensured and it is installed horizontally in
level?
• Have you connected refrigeration pipes properly?
• Have you checked the external surface and the internal part of the outdoor unit?
• Is there any possibility of short circuit due to the heat of an outdoor unit?
• Is the place well-ventilated and ensures space for service?
• Is the outdoor unit fixed securely?
• Have you checked for any gas leakage?
• Are the length and the height difference between the refrigerant pipes within the allowable
range?
• Have you properly insulated pipes?
• Is the quantity of the additional refrigerant correctly weighed in?
• You must record the amount of additional refrigerant charging on the service record label
placed outside the outdoor unit.
• Have you completed the drain test?
• Is the drainpipe properly insulated?
• Have you checked for interference between the power and the communication cable?
• Have you performed the earthing work 3 to the outdoor unit?
• Is the length of the wire within allowable range?
• Is the wiring route correct?
• Have you used verified power supply cable and the communication cable?
• Check whether the vibration-resistance frame is correctly installed if there is a possible
vibration of the outdoor unit.