  Step 2: Commissioning and Configuring the Installation
Setting Country, Grid and Language
The inverter must be configured to the proper settings in order to ensure that it
complies with the country grid code and functions. Unless these settings are selected,
the inverter will not start production.
 1. From the Commissioning screen, select Country & Grid.
 2. From the Country & Grid drop-down list, select the required option and tap Set
Country & Grid.
 3. If relevant, from the Language drop-down list, select your language and tap Set
Language.
 4. To save the information to a read-only file, tap the PDF icon (iOS) or the JPEG icon
(Android) at the bottom of the screen.
Pairing
 1. From the Commissioning menu, select Pairing.
 2. Tap Start Pairing.
 3. When Pairing Complete is displayed, the system startup process begins:
Since the inverter is ON, the Power Optimizers start producing power and the
inverter starts converting AC.
WARNING!
When you turn ON the inverter ON/OFF/P switch, the DC cables carry a high
Voltage and the Power Optimizers no longer output a safe output.
 
AVERTISSEMENT!
Après avoir mis l'interrupteur ON/OFF/P de l'onduleur monophasé sur ON,
les câbles DC portent une haute tension et les optimiseurs de puissance ne
 
génèrent plus la tension de sécurité.
When the inverter starts converting power after the initial connection to the AC, the
inverter enters Wake up mode until its working voltage is reached. This mode is
indicated by the flickering green inverter LED.
When working voltage is reached, the inverter enters Production mode and
produces power. The steadily lit green inverter LED indicates this mode.
 4. Tap OK to return to the Commissioning menu.