8.10.8 Battery Forced Charge Time

Tap Settings→Energy Management Parameter→Battery Forced Charge Time to enter
the corresponding screen.
When there is no PV power, the power imported from the grid charges the energy system
during the time period until the target SOC is reached.
It is recommended to set the time period in off-peak tariff time. The time period 1 is in priority
to the time period 2 if two periods overlap. The charging energy comes from the excess PV
energy in priority and then from the grid. The inverter will take charging power from the grid
in the case of PV energy shortage.

8.10.9 Load Control

Tap Settings→Energy Management Parameter→Load Control to enter the correspond-
ing screen, on which you can set Load Control Mode. Load Control Mode includes Timing
Mode, Switch Mode, and Intelligent Mode.
figure 8-20 Battery Discharge Time
figure 8-21 Battery Forced Charge Time
8 iSolarCloud App
95

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the SH5.0RT and is the answer not in the manual?

This manual is also suitable for:

Sh6.0rtSh8.0rtSh10rt

Table of Contents