1-4. RIGGING

In case that a chiller is lifted up, check first weight of the chiller by referring its contract
specifications and then choose and use suitable lifting wires and shackles. Since 4 holes are
provided on the conners of upper tube sheet, use the holes to lift the chiller. Note that the
angle of wires shall be within 60 deg. Please refer to Exhibit B.

1-5. SLIDING

In case that sliding of the chiller is required, using tiltdozers (trail-builders) is recommended.
If a wire to slide the chiller is used, the wire shall be connected as shown in the figure below.

1-6. SETTING ON THE FOUNDATION

Please refer the foundation to Exhibit C.
Please set the Chiller on the foundation bolt position.
φ30(LJ-01)
φ40(LJ-02/03)
wire