3 - HANDLING
The unit can be handled by slings, lifting beam or stacker.
In all cases, the lifting point has to be at the base of the unit. For packaged units or assembled multi-block units, the centre of gravity
is at the centre of the unit.
This operation will be performed by qualified personnel.
The unit must be handled with care, and only in the horizontal
position. If the unit is handled by a lifting beam + slings, tubes
need to be placed in the holes provided in the support feet.
Ensure that the crane hook adapter is large enough to prevent
the belts applying any pressure to the AHU casing. Furthermore,
ensure that the steel tubes are secured to prevent any movement.
If the above-mentioned lifting methods cannot be used, the unit
may be lifted using a forklift truck, taking great care not to dent
the lower panel (use forks of a sufficient length).
Follow the applicable handling rules.
39HXC, 39HXE and 39HXEZ models
Procedure for uncoupling 39HX multi-blocks or assembling the 2 blocks for the 39HXEZ 100 & 150
1 Remove the 4 nuts and screws
2
Undo the screws on each beam and remove them.
C
5