NewMar SOL 20 Quick Start Manual page 4

Solar charging system

Advertisement

Figure 1: Installation Overview
Solar Panel
6.0 Installaion
A. Solar panel wiring preparation (reference Figure 2 & 3)
WARNING: DO NOT REMOVE THE CARDBOARD COVERING THE PVC SIDE OF PANEL UNITL THE
INSTALLATION IS COMPLETED. ONCE CABLES ARE CONNECTED TO THE PANEL'S JUNCTION BOX THE
CABLES WILL BECOME LIVE IF THE PANEL IS EXPOSED TO A LIGHT SOURCE.
Figure 2: Junction Box
Cable Clamp
1) Locate the black junction box on the rear of the solar panel and remove the two Philips head screws
on the junction box cover, and open.
2) Unscrew the cord grip nut on the outside of box and remove it and the rubber grommet. Feed the end of
the 12/2 provided cable which has the two # 8 ring lugs attached through the nut, grommet and the
fitting body attached to the box and loosely re-fit the nut back on to the fitting. Note: Two junction box holes
are provided with a cord grip installed in one and a watertight hole seal in the other. The cord grip and hole
P.O. Box 1306
Newport Beach
California 92663
Negative
Positive
www.newmarEVpower.com
Charge Controller
Battery Fuse
Figure 3: Junction Box Close Up
Cord Grip
Nut
Positive
(+)
Vehicle Battery
Hole Seal
Negative
(-)