Two-pass placement method involves hanging and lashing the distribution cable to a pre-existing
cable or a dedicated messenger in two passes. The reel is typically loaded onto a trailer that is placed
at the field side end of the run. The technician pulls off the CO end of the cable, starts hanging the
cable on blocks, and then progresses towards the CO end of the run. See
Figure
12. Once the
complete cable is hung, the technician returns to the field side end of the cable and begins the lashing
operation, removing the blocks as he progresses. See
Figure
13. When a TAP over mold is reached,
the lashing machine is lifted past the over mold and tether and strand are secured before continuing.
Figure 12. First Pass - Hang on Blocking, Pull End to Beginning
Figure 13. Second Pass - Lash, Remove Blocking
Page 7
© 2007, ADC Telecommunications, Inc.

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the OmniReach and is the answer not in the manual?

Table of Contents