Procedure
Step 1 Label each cable based on the corresponding ports on the eLight actuator.
Step 2 Remove cables from the eLight actuator.
Step 3 Remove the old eLight actuator from guide rails.
Step 4 Install the new eLight actuator in the correct position and connect the cables.
Step 5 Check the parameters and communication status of the eLight actuator to ensure
normal communication.
Step 6 On the ECC800-Pro WebUI, choose Maintenance > Deployment Wizard >
Linkage Test > eLight Actuator Commissioning and click Test. The eLight strip
light is lit up in red, green, blue, and white in sequence for 3 seconds respectively,
and then turns off.
----End

5.4.25 Replacing an eLight Power Supply

Impact on the System
The eLight strip light is off during replacement.
Preparations
Issue 01 (2020-12-25)
Tools: ESD gloves, Phillips screwdriver, step ladder, label, marker
Material: eLight power supply
Copyright © Huawei Technologies Co., Ltd.
5 Parts Replacement
129

Advertisement

Table of Contents
loading

Table of Contents