Grounding The Stack Switchgear - Nuvation Energy NUVSSG-1250-100 Product Manual

High-voltage bms
Table of Contents

Advertisement

Power In
An inline breaker provides the ability to turn off input power for the Stack Switchgear. Ensure the
breaker is in the OFF position.
Verify system is de-energized
Using a multimeter check the Battery Stack and the DC Bus terminals respectively to verify that
the system is de-energized. Be aware that battery itself cannot be de-energized and in some
situations, it may not be possible to de-energize the DC bus.

4.2.3. Grounding the Stack Switchgear

The Stack Switchgear must be bonded to the rack or Earth through a suitably sized conductor by NEC
standards. From NFPA 70, Table 250.122, the wire size must be chosen based on the rating of the
automatic over-current device in the circuit, as shown in
An M8 lug (not included) should be used (e.g. Panduit Corp LCMA50-8-L), along with an M8 screw
and tooth lock washer (included), as shown in
In order to make the connection:
Document ID: NE-PM-003
Figure 14. Power In Breaker
Figure 15. Grounding stud
Table 3. Minimum grounding wire size
Stack Switchgear
Current Rating (A)
100
200
300
Nuvation Energy High-Voltage BMS - Product Manual
Table
3.
Grounding Wire (AWG)
Copper
Aluminum
8
6
4
Figure
15.
17
6
4
2
Rev 1.2, 2021-03-03