8. OPERATION INSTRUCTIONS

8.1 ENERGIZING

Check if there are foreign objects in the switchgear.
Check the connections of the switchgear.

PHASE CONFORMITY TEST

If the phases conform, light is OFF .
If the phases do not conform, light is ON.
(Test device cannot be delivered with switchgear.)

CABLE TEST

In Output Switchgear
To check cable faults.
Turn the breaker ON.
Turn the disconnector ON.
Turn the earthing disconnector OFF .
Open the switchgear front cover.
Place the cable test device.
Turn the earthing disconnector ON.
Perform the required measurements.
6
Ulusoy URING12-24 - LLF - SF Insulated Compact RMU Switchgear with Fuse User Manual May 2020 www.eaton.com
Serial Light
6
Place the switchgear front cover.
Voltage Indicator
Input switchgear:
When input cables are powered, voltage indicator lights
must be ON.
Output switchgear:
When the disconnector and breaker are OFF ,
voltage indicator lights must be ON.
In Input Switchgear
To check cable faults.
Turn the breaker ON.
Turn the disconnector ON.
Break the power of the switchgear from previous
center and perform the earthing of the cables.
Turn the earthing disconnector OFF .
Open the switchgear front cover.
Place the cable test device.
Turn the earthing disconnector ON from both sides.
Perform the required measurements.