AKD-10—Install Accessories
AKD-10—Secondary Disconnects
This section deals with installing and wiring the legacy secondary disconnect assemblies onto the
EntelliGuard R breaker . Installing the secondary disconnect assembly consists of doing these tasks:
Installing the secondary disconnect assembly (Figure 14, Figure 15, and Figure 16).
Wiring the secondary disconnect assembly (Table 8 shows the WavePro secondary disconnect terminals).
The EntelliGuard R Retrofill Breaker has these three options:
One secondary disconnect installed
Two secondary disconnects installed
No secondary disconnects installed
Figure 14. AKD-10 Secondary Disconnects View 1
EntelliGuard R Circuit Breaker Retrofill AKD-10 Installation Manual
26
WIRING
• Before installing the breaker, the
secondary disconnects must be wired
to the EntelliGuard R Breaker.
• Wires with wire markers are provided
on the breaker . Make sure that the
switchgear wiring connection points
match up with the original wiring of the
cubicle. This ensures that all wiring
connections are properly made.
Wrong connections will cause the
breaker to malfunction.
Figure 15. AKD-10 Secondary Disconnects View 2
DEH41550 R06