5.3 Mounting versions

Explanation of the installation variants depending on the roof construction or design variants.
MV 1 – Flush base troughs on system edge
e
A
e
Edge
A
MV 2 – Module fastening long side
MV 3 – Base troughs for cross drainage
max. 100 mm
MV 4 – Installation of expansion joints
in the base troughs
e
M
e
joint
M
1
max. 610 mm
Alternatively, the first base trough at the system
edge / expansion joint must be installed flush with
the modules, the subsequent troughs must be
positioned centrally beneath the module joint.
Prerequisite:
Flat roof end clamp (MV 2)
System edge / expansion joint:
e
Module joint:
e
joint
Place the drilling screw from the flat roof end clamp
centred over the screw channel of the base foot or
module support and screw in.
Tightening torque max. 6 Nm.
The screw must not be overtightened!
Approval from manufacturer required for clamping
in the corner section of the long frame side.
If the base troughs 150-30 for cross drainage end
without PE pads, stick additional PE pad (1) onto
these troughs
Max. 100 mm. extension over PE-pad
Distance between PE pads: max. 610 mm
Shorten PE-pad to the required length if needed
Push the base trough expansion joint centrally into
the adjacent base troughs. A gap of 50 mm must
remain between the ends of the rails. Screw the
expansion joints to the base troughs. On the
moving side, the two screws must be screwed into
50
the base trough so that they are centred in the
slots.
Do not install the expansion joint below a module.
Max. base trough length with the base trough
expansion joint approx. 34 m, plan for proper
expansion joints after this.
10
Approval module manufacturer
for module clamping
= module length – 69 mm
A
= module length + 12 mm
M

Advertisement

Table of Contents
loading

This manual is also suitable for:

Novotegra east-west ii

Table of Contents