Piping Requirements
Every system is different, built to suit the
customer.
Typical system will include piping layout/ system
design drawings provided by either approved
project engineering staff or qualified Walinga
personnel.
All piping installed must be properly supported.
When installing the support points, ensure
that there is enough strength to support a full
pipe line, should the system become
plugged.
One support point every 10' is
recommended.
Ensure that the main lines are as straight as
possible to maintain maximum conveying rate.
Space the inlets and the inlet piping, at a maximum of 40' apart. Or in accordance with
piping layout drawing provided.
When installing the inlet lines, ensure that the Y elbows enter from either the side or
the top of the main pipe line. The Y must also follow the flow of the product and air
stream.
All the piping should be within 400' of the main
Central Vac system to maintain product air
speed and avoid plugging
All compression couplers must be fully tightened,
ensuring a proper seal.
Grounding strip must be properly installed,
making contact to both pipes, to ensure total
protection from static electricity build up.