Huawei PTN Series Quick Installation Manual page 15

Transport platform
Hide thumbs Also See for PTN Series:
Table of Contents

Advertisement

Appendix
1 Assembling OT Terminals and Power Cables
Components of a one-hole OT terminal and a power cable
Heat shrink
tubing
Single-hole
OT bare
crimp
terminal
Conductor of
the power cable
Components of a two-hole OT terminal and a power cable
Dual-hole
OT bare
crimp
terminal
Conductor of
the power cable
Mapping between the cross-
sectional area of the conductor
and the value of L
Cross-Sectional
Value of L1
Area of the
(mm)
Conductor (mm² )
1
1.5
2.5
4
6
10
16
25
35
50
Insulation layer of
the power cable
Heat shrink
tubing
Insulation layer of the
power cable
Procedure
1. Based on the cross-sectional
area of the cable conductor,
strip a part of insulation
coating C to expose the
conductor D of length L1.
2. Put the heat shrink tubing
onto the bare crimping
terminal.
3. Put the OT terminal B onto
7
the exposed conductor, and
7
ensure that the OT terminal
is in good contact with the
7
insulation coating C.
8
4. Crimp the joint parts of the
bare crimp terminal and the
9
conductor.
11
5. Push the heat shrink tubing
toward the connector until
13
the tube covers the crimped
14
part, and then use a heat gun
to heat the tube.
16
16
Peeling a power cable
Heat shrink tubing and bare crimp terminal
Crimping the joint parts of the bare crimp terminal
and the conductor (OT terminal)
Heating the heat shrink tubing
13