Aileron Rigging - Rans S-7S COURIER Text Manual

Table of Contents

Advertisement

AILERON RIGGING

Neutral position and cable tension
(AFTER WING INSTALLATION/ AFTER SETTING OF WASHOUT)
8.
Center forward control stick in neutral position (aileron neutral) and
securely fix in this position.
9.
By adjusting the turnbuckles set the aileron bell cranks to neutral position
as shown in FIGURE 09A-09. With the stick centered and the bell cranks
in neutral position, the cables should be tight.
10.
Without a cable tension meter, adjusting the cables will have to be an
educated guess. The correct tension does not overload or "drag" the
system, nor will cables feel spongy. If you have a cable tension meter
refer to FIGURE 09-07 for tension information.
11.
Using the modified wing washout rigging board as shown in FIGURE 09A-
01. Hold the rigging board so that it is contacting the bottom side of the
leading edge spar and the bottom side of the trailing edge spar at
approximate aileron half span. The trailing edge of the aileron should rest
on the shim (level with lower surface of both spars).
12.
With the control sticks and bell cranks neutral install the short aileron push
pull tube. CAUTION: Rod Ends must be turned into the push pull tube at
least 10 complete turns.
13.
Tighten all connections and check.
Deflections
14.
For deflection measurements center control stick for neutral position,
move and hold control stick against stop and measure.
15.
Measurement is taken on top surface of aileron at approximate half span
on top of aileron rib. Deflection angle is in reference to trailing edge of
Aileron.
16.
Adjust aileron stops as required. Reference also FIGURE 02-02. Make
sure the Aileron Leading Edge is not contacting the Aileron Hinge.
Up:
Down:
33
(Tolerance is +2.0 / -1.0 )
30
(Tolerance is +2.0 / -1.0 )
09A-02
06/15/2011

Advertisement

Table of Contents
loading

Table of Contents