Figure 7-12 Installing a button board
Step 7 Reconnect the cables to the button board based on the recorded information.
Step 8 Place the SMU cover in position and tighten the screws.
Step 9 Reconnect the cables to the RJ45 ports on the SMU based on the recorded information.
Step 10 Disconnect the ground cable for the ESD wrist strap, and take off the ESD wrist strap and
ESD gloves.
----End

7.3 Replacing the Power Distribution Monitoring Unit

7.3.1 Replacing the Signal Sampling Board

Prerequisites
Context
To replace the signal sampling board, you do not need to disconnect the AC input to the
power system.
Issue 07 (2020-04-10)
You have obtained an ESD wrist strap, a pair of ESD gloves, an ESD box or bag, a tool
kit, and the cabinet door key.
The new signal sampling board is intact.