1. Push the machine to the final location.
2. Connect the power cable to the net entry.
3. Connect the power cable to the wall socket.
4.2.3

Level the machine

1. Move down the adjustable feet (A) until the wheels (B) are off
the ground.
2. Adjust the height of the feet and make sure that the machine
is leveled.
3. Tighten the nuts (C) to lock the feet.
4.3

Finish the installation

1. Turn on the machine. See § 3.2.1.
WARNlNG
Mind the minimum requirement of the load
capacity of the floor. See § 6.2.
Note
Make sure the final location is well-lit and well-
ventilated.
Note
Make sure that the on/of key and power cable are
freely accessible.