Commissioning

2.9.1
Visual inspection
Before powering the detector, inspect the following:
Refer to
Figure 2-13: Components of the GDU-Incus
A. Display
B. Sensor (four positions)
C. Sensor pod (four positions)
D. Mounting bracket
E. Enclosure mounting point
F. Terminal cover bolts (six positions). Tighten to 9 Nm.
G. Terminal cover
H. External earth point
I. Main enclosure bolts (six positions). Do not remove or adjust.
Ensure detector is correctly situated for area of detection.
Ensure mounting bracket is secured to mounting points on the detector and mounting
surface/pole.
Check pole mount (if present) for suitability to withstand detector weight and
measurement
Ensure external earth is correctly attached using spring washer.
Ensure correct cable gland installation and appropriate certification or local regulations
have been observed. Check correct cable installation in the terminal compartment;
ensure terminal compartment flame paths and seals are intact.
Ensure incoming cable is threaded through ferrite beads
Reference Manual
Figure 2-13
for key locations on the GDU-Incus when completing this inspection.
Installation
December 2020
(Figure
2-8).
27

Advertisement

Table of Contents
loading

Table of Contents