Tower
Foundation
2005 NEC Section
Topic
Article 250.52, item 5
Tower Grounding
Article 250.53, item A
Tower Grounding
Article 250.53, item G
Grounding Electrode Installation
Article 250.64
Grounding Conductor Routing and Placement
Article 250.66, item A
Grounding Conductor Size
Article 270.70
Bonding of Grounding Conductor
AIR 40, AIR Breeze, AIR 30, AIR X MARINE and AIR SILENT-X are trademarks of Primus Wind Power 2013 Primus Wind Power Inc.
Cable Clamp
Grounding Conductor
6 AWG minimum.
Must be secured and
1 ft.
Grounding Wire Clamp
(0.3 m)
Grounding Rod
Existing Grade
8 ft.
(2.44m)
WIRE CONNECTIONS TO AIR WIND TURBINE
WARNING:
Do not connect wires to batteries until all electrical
connections are completed.
Secure connections using "split bolt" or solder connectors. Use color coded
wires - red for battery positive, black for battery negative, and green for
earth ground. Size wiring based on wiring tables provided. Insulate connec-
tions with heat shrink tubing or good quality electrical tape. Leave suffi-
cient service loop in the wires to accommodate removal of the turbine
from the tower.
FINAL CONNECTIONS
Follow system wiring diagram and run wires to disconnect switch, fuse or
circuit breaker and ammeter.
Before making battery connections, make sure circuit breakers and stop
switch (highly recommended) are in the OFF position. Attach wires to
battery; red to positive battery terminal and black to negative battery
terminal.
WARNING:
Reversed wire connections will damage the AIR wind
turbine's electronics. The polarity of the AIR wind turbine's wires may be
checked by connecting a voltmeter to the wires and spinning the rotor
by hand.
Complete battery connections and switch ON circuit breakers and stop
switch. When power is switched on, the turbine LED will illuminate for two
seconds, go off for two seconds and illuminate for four seconds. This indi-
cates the internal
controller is functioning. The LED remains illuminated if the turbine is
charging the battery.
The installation is now complete.
AIR Owner's Manual
29
3-CMLT-2020-A

Hide quick links:

Advertisement

Table of Contents
loading

Related Products for Primus Wind Power AIR 40

This manual is also suitable for:

Air breezeAir 30Air x marineAir silent-x

Table of Contents