TURBINE ASSEMBLY
STEP 2: Mount Blade Hub to Turbine
Assembled blade
hub
1.) Coat rotor shaft threads and blade hub with Tef Gel.
2.) Slide blade hub onto rotor shaft.
3.) Start 5/8-18 jam nut on rotor shaft.
4.) Carefully and slowly "spin" the blades to begin tightening the nut.
AIR 40, AIR Breeze, AIR 30, AIR X MARINE and AIR SILENT-X are trademarks of Primus Wind Power 2013 Primus Wind Power Inc.
Rotor shaft
5.) Insert 5/16" hex wrench in rotor shaft.
6.) Carefully and slowly "spin" the blades to completely secure the blade
hub to the turbine.
7.) Apply the following torque when tightening the Rotor Jam Nut using
torque wrench at 40 ft.lbs. / 55 Nm.
NOTE: When The Shaft and Face are exposed, apply a liberal
amount of synthetic grease to the gap around Shaft and Bearing
on the Face of the turbine (this should be performed as a regular
maintenance event every 12 months). See FAQ section on storage
kit recommendations and Appendix C
IMPORTANT:
Tef-Gel is a corrosion inhibitor and is especially
important in marine applications. Tef-Gel should be applied to all
blade bolts and yaw bolts using the applicator and Tef-Gel provid-
ed with your hardware kit. Tef-Gel helps to prevent corrosion and
lubricates threads (recommended for both land and marine us-
age).
IMPORTANT:
Observe torque specs
AIR Owner's Manual
13
3-CMLT-2020-A

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Air breezeAir 30Air x marineAir silent-x

Table of Contents