Installation Information - M&C SP2500-H Series Instruction Manual

Gas sample probe
Table of Contents

Advertisement

11

INSTALLATION INFORMATION

When carrying out installation, the safety rules and regulations for the prevention of accidents must be
observed – this applies similarly to subsequent operation. The information in Chapter 3 "Important
safety information" must be observed in particular.
The following applies:
Select an optimal sample point according to the general guidelines or agree on a sample point with
the responsible authorities.
The sample point should be arranged so that sufficient space for installation and removal of the
probe is available; the insertion length of the sample tube should be taken into account.
Easy access to the probe must be ensured for any necessary maintenance.
The sample nozzle locally should be dimensioned so that the nozzle temperature is always above
the acid dew point to prevent corrosion and blockages.
If the ambient temperature in the area of the nozzle is higher than 60°C due to the radiated heat, a
radiant heat reflective plate must be installed in the area of the nozzle locally to protect the probe.
The nozzle mounting flange connection should be DN65 PN6 or 3"ANSI (115V version). For other
connection dimensions, an optional intermediate flange adapter is available. The necessary,
minimum flange sizes or minimal nozzle diameter depends on the sample tube used or the
preliminary filter diameter.
It is recommended to mount the probe horizontally with an angle of inclination of 10° with respect to
the process.
The suitability of the probe must be verified prior to installation by comparison with
the available operating parameters (see rating plate).
Note
14
SP2500-H | 1.00.02
www.mc-techgroup.com

Advertisement

Table of Contents
loading

Table of Contents