SECTION 2 INSTALLATION CONSIDERATIONS

BEFORE START UP

You must complete the following before start up is attempted.
Check that all parts have the identical serial numbers.
Measure and record flange -to-flange distance to verify it is the same as final check out sheet.
If you are using a recorder, DAS, etc.,
other sources should be left off until system has been completely checked according to the following instructions.
After system operation has been verified connect and test external connections.
Read the instructions first to familiarize yourself with the instrument before attempting start up.
The air purge and Weather cover system, Transceiver, Retro reflector, Service module must be installed and power
applied.
Control unit must be installed and wired to the service module and customers equipment as applicable.
All wiring and mechanical installations must be complete per drawings provided in this manual. All wiring must be
checked and power applied to both the control unit and the stack maintenance module.
Beam Alignment procedure has been completed.
CONTROLUNIT GLOSSARY OF TERMS
OUTPUT TYPE SETUP – "Output type" refers to the 4-20mA outputs.
Instant opacity, z/s outputted during calibration cycle.
Average, opacity average z/s outputted during cal cycle.
Last - instant opacity, last value is held during cal cycle.
Note: Last should be used if you are using the output for process control signal.
ALARM AUTO/MANUAL SETUP – Press return/enter button to enter. Choose between 1-auto or 2- manual.
Auto means when the high opacity alarm has been activated and when the level of smoke drops below the alarm point the
alarm contacts 02 & 04 and icon will reset automatically.
Manual reset means when the high opacity alarm has been activated, pushing the return/enter button 04 contact will de-
energize but 02 will remain energized. When the level of smoke drops below the alarm point the return/enter button is
pushed and both 02 &04 will be de-energised.
OUTPUT SCALING SETUP – Press return/enter button to enter.
DO NOT CONNECT THEM NOW.