After completing the installation of AC modules on the rooftop or other site, next step is to install the
communication gateway (EnerBox2). Before installing the gateway, adhere to the following notices:
• For reliable communication, it is recommended for the gateway (EnerBox2) to be directly installed
to an outlet which is electrically connected to the distribution panel where the AC modules are
also attached.
• To avoid damage and failure of the gateway, do not use at temperatures outside of 0 ~ 40°C (32
~ 104°F).
• To avoid damage of the gateway, install the gateway in an environmentally protected location.
• To avoid malfunction of the gateway, be sure to use only the enclosed adapter and cables.
• To avoid risk of the electric shock, do not disassemble or expose to pressure.
• To avoid risk of the electric shock, do not bend or cut cables used to connect to the gateway.
• Do not expose to water.
• Only clean with a dry cloth.
• The gateway will not log energy production if the power of the gateway (EnerBox2) is off or AC
cable and PLC (Power Line Communication) are disconnected. So always keep the gateway on.
• EnerBox2's warranty may be void if cover removed. No serviceable parts inside.
• To avoid communication interference, do not connect the product to surge protector or
surge protector-embedded power strips.
• It is recommended the gateway is directly connected to a 120VAC outlet.
Rev. 1.0
AC Module System Installation Manual