3-13 Grid Voltage Measurement

Measure AC voltage of the utility at the distribution panel and AC junction box using a voltmeter. Fill
out the below table. If the measured voltage is out of the range which is specified in each table, ask a local
electricity provider about voltage instability.
An array of AC modules
At distribution panel
Single Phase 240V(RMS)
Measure point
Expected
L1 – N
120
L2 – N
120
L3 – N
-
L1 – L2
240
L2 – L3
-
L3 – L1
-
At AC junction box
Single Phase 240V(RMS)
Measure point
Expected
L1 – N
120
L2 – N
120
L3 – N
-
L1 – L2
240
L2 – L3
-
L3 – L1
-
Plan the installation work in moderate weather. There is a risk of electric shock when it is snowing or raining.
To prevent the risk of accidents, use proper PPE (Personal Protective Equipment) including helmets, eye
protection and gloves at all times.
If installation location is high above ground, make sure to use Fall Protection System during
installation.
For safety, only qualified personnel should perform the services.
Rev. 1.0
AC Module System Installation Manual
Leave the transition
cable disconnected
AC junction box
Range
Measured
Expected
106~132
120
106~132
120
211~264
208
Range
Measured
Expected
106~132
120
106~132
120
211~264
208
Copyright © 2020 LG Electronics.
All Rights Reserved.
Voltage
measure
Single Phase 208V(RMS)
Range
Measured
106~132
106~132
-
183~229
Single Phase 208V(RMS)
Range
Measured
106~132
106~132
-
183~229
Meter
G
N L1 L2
Distribution pan
el
Three Phase 208V(RMS) Merge,
Split Type
Expected
Range
Measured
120
106~132
120
106~132
120
106~132
208
183~229
208
183~229
208
183~229
Three Phase 208V(RMS) Merge,
Split Type
Expected
Range
Measured
120
106~132
120
106~132
120
106~132
208
183~229
208
183~229
208
183~229
45