Step 4B Three (3) Phase, 3W+PE - Connect 200-240 3-Phase AC Input section
Rectifier Positions Powered
Sizing external protectors and wire for all rectifier positions (3 or 6) provides full power for all rectifier positions.
1. Verify the charger AC breaker (AC1) is OFF.
2. Verify AC voltage matches AC Input per Charger Label with a meter.
3. Bring AC wires into the AC Input Box in conduit through one of the 2"
knockouts
4. Connect Ground wire (green /green-yellow) to lug.
5. Strip 1/2" (13mm)
6. Insert into ground lug.
7. Tighten lug screw securely.
8. Pull wire to verify.
5. Connect each AC wire to the terminal
block in the AC Input Box.
AC terminal connections are labeled at each
position—Gnd, L, N, L1, and L2.
a. Strip 1/4" (10mm).
b. Insert into terminal block.
c. Torque screw to 13 in-lb (1.5 Nm).
d. Pull wire to verify.
Go to Step 5
8
Recommended External Protection and Minimum Wire Size—6 AWG max.
1
2
3
Top Feed
Bottom Feed
Integritas Wall Mount Charger - Quick Start Guide
Document 8600092587P r03 2018 August
Maximum
Rectifiers
External Feed Protector
per Feed
1
15A
2
30A
3
40A
200-240V~ Phase to Phase
(2725W per rectifier max)
Three (3) Phase Rectifiers
Minimum Wire
14AWG
10AWG
8AWG
240V