4.4.

INSTRUCTIONS FOR PUTTING MACHINE INTO SERVICE.

During manufacture, each machine is subject to continuous quality checks. Shipping may cause damage, in
which case you must record it in a written complaint to the carrier before first operation.
Reminder: Before use, familiarise yourself with the machine by referring to this manual and to the
instructions on the plates.

4.4.1. Ground controls.

See photo 1.
1 - Low oil pressure indicator light.
2 - Low battery charge indicator.
3 - Air filter clogging indicator.
4 - Hour-meter.
5 - Platform up/down control switch.
6 - Beacon control (option).
7 - Battery tester - hour-meter (bi-energy).
8 - Engine start switch.
9 - Emergency stop key button.
10 - Tilt sensor.

4.4.2. Platform controls.

See photo 2.
1 - Stabiliser (4) controls - (option).
2 - Buzzer control.
3 - Speed control.
4 - Platform stow control.
5 - Engine start
6 - Platform up/down or travel select switch
7 - Differential lock
8 - Diesel / electric select switch (bi-energy)
9 - Emergency stop button
10 - Movement control handle

4.4.3. Fitting the guardrails.

Photo 3 : locking pins.
The machine is delivered with the guardrails not fitted. They must be installed and locked with pins (arrows,
photo 3). Ensure that safety bar (arrow, photo 4) can slide freely to permit access to platform.
2
1
5
4
7
8
Photo 1 : Ground controls.
1
6
8
Photo 2 : Platforms controls.
Photo 4 : Safety bar.
26
3
6
10
9
2
3
4
9
7
5
10

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

H12 sdxH12 sdeH15 sdH15 sdxH15 sdeH18 sdx

Table of Contents