Procedure
installed power supply tray is operational and that its status
light is on.
1. Open the front door to the cabinet.
2. Verify that the circuit breaker on the PEP to the line (LINE
1 or LINE 2) that will power the power supply tray to be
C2
installed is off.
3. Slide the new power supply tray into the power chassis and
push until it firmly connects with the power chassis.
4. Turn the two thumbscrews (Figure PR5-1) clockwise to
secure the power supply tray to the power chassis.
5. Plug the power cord into the front of the power supply tray
and secure it with the wire retaining clip.
6. Check the circulation vents on the power supply trays and
power chassis and make sure they are free of air flow
obstructions.
7. Turn the proper circuit breaker on the PEP to the on
position.
8. Verify that the status LED is lit.
PR5 - 4
WBPEEUI210509A1