For Icm In Operation; Installation Instructions - Danfoss ICAD Series Installation Manual

Mechanical installation on icm
Table of Contents

Advertisement

For ICM in operation

When ICAD is installed/serviced, on a cold/frozen valve; do the following:
1. Make sure the old grease is totally removed before mounting a new EPDM
O-ring and PTFE support ring.
2. If there is any ice or moisture present, it must be removed prior to applying
the grease. The ice/moisture can be removed with an electrical hot air gun.
3. After ice removal by heater, ensure that the ICM adapter is totally dry before
mounting new EPDM O-ring and PTFE support ring
4. Install the ICAD actuator on the ICM adapter making sure it is pushed
completely down. Fasten the the 3 set screws using a 2.5 mm hexagon key.
Note!
Crosstighthen all 3 screws to ensure equal tightening.
Max 3 Nm torque.
2 | AN331637222900en-000101
© Danfoss | DCS (ms) | 2020.01

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the ICAD Series and is the answer not in the manual?

Questions and answers

Table of Contents