3.2.4

Preparation for Installation

 Installation Space
Secure sufficient working space for easy operation, cleaning, maintenance, and inspection.
 Illumination
Prepare illumination devices which allow easy operation, cleaning, maintenance, and inspection.
 Ventilation
If natural ventilation is insufficient, install ventilation fans according to the relevant regulations.
 Piping
Item
Suction gas inlet
Low-stage gas outlet
High-stage gas inlet
High-stage discharge gas outlet
Lubrication oil supply port for low-stage
bearing (journal)
Lubrication oil supply port for low-stage
capacity control (increased side)
Lubrication oil supply port for low-stage
capacity control (decreased side)
Oil supply port for oil injection
Lubrication oil supply port for high-stage
bearing (journal)
Lubrication oil supply port for high-stage
capacity control (increased side)
Lubrication oil supply port for high-stage
capacity control (decreased side)
15A
20A
25A
80A
100A
150A
Compound 2-stage Screw Compressor 2016**C
Table 3-1 List of Connecting Pipes (Compressor)
D
t
74
5
84
5
100
5
200
5
225
5
305
5
Figure 3-2 Dimensions of the Joint
Dimensions
JIS 20K 150A (6")
JIS 20K 100A (4")
JIS 20K 100A (4")
JIS 20K 80A (3")
JIS 20K 25A (1")
Rc1/4
Rc3/8
JIS 20K 15A (1/2")
JIS 20K 20A (3/4")
Rc3/8
Rc1/4
g
C
N-h
43
70
4-M12
51
75
4-M12
61
90
4-M16
121
160
8-M20
146
185
8-M20
216
260
12-M22
3-4
2200LZJE-HO-C6-N_2013.12.
Chapter 3 Installation
Remarks
See Figure 3-2.
See Figure 3-2.
See Figure 3-2.
See Figure 3-2.
y
25
25
25
35
35
34
3.2 Installation Works

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the 2016 C Series and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

This manual is also suitable for:

2016llc2016lmc2016lsc2016msc2016ssc

Table of Contents

Save PDF