 The compressor eye bolts must not be used for lifting the unit. To lift the unit, use
the lifting chains provided around the base or other lifting means provided on the
base.
Check path of compressor installation to make sure it is free of obstacles in consideration of the
5.
compressor size.
Before lifting, check that the hook is located above the gravity center of the compressor.
6.
Direct all the workers to stay clear of the work site before lifting.
7.
Before lifting the compressor, alert all workers in area of dangers during lifting process by signal
8.
(such as calling at the beginning of the work or making a signal by hand). Do not lift the
compressor unless the signals (such as calling out or hand signals) are completely understood by
the workers at site.
Slowly reel up the wire ropes until immediately before the compressor leaves the ground.
9.
Then, reel up the wire ropes a little further until the compressor is slightly up away from the ground.
10.
Check that the compressor is not tilted. If the compressor is tilted, return the compressor to the
ground and correct the tilt by adjusting the wire ropes. After that, restart the lifting operation.
Be sure to lift up the compressor slowly. If it is lifted rapidly, it may damage the lifting tools such as
11.
wire ropes or a part of the compressor.
When the lifting work starts, observe to see if wire ropes and lifting tools are normal. Be sure that
12.
the compressor is not tilted.
When moving the lifted compressor, always use guiding ropes.
13.
When moving the compressor, turn away workers from the movement direction and check safety.
14.
Do not lift the compressor above the safety passage unless absolutely necessary.
15.
Do not lower the compressor on the safety passage. Always keep the safety passage free of
16.
obstacles.
Remove any obstacles before lowering the compressor onto the ground. The compressor should
17.
not be tilted or unstable.
Before lowering the compressor, announce to the workers around the working area in advance.
18.
When lowering the compressor onto two or more blocks, align the tops of blocks so that the
19.
compressor becomes stable horizontally on them.
Slowly lower the lifted compressor so that it is not damaged by shock.
20.
Compound 2-stage Screw Compressor 2016**C
3-2
2200LZJE-HO-C6-N_2013.12.
Chapter 3 Installation
3.2 Installation Works

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the 2016 C Series and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

This manual is also suitable for:

2016llc2016lmc2016lsc2016msc2016ssc

Table of Contents

Save PDF