Step 2:
Position Base Plate
1. Position the edge of AL
of ½" [12.5mm] from the inside edge of rim joist.
As shown in Fig. 1.
Fig. 1
1/2"
[12.5mm]
Step 3:
Max Post Spacing
• 6' panel maximum post spacing is 69-3/4" [1771.5mm].
Note:
• Do not exceed the maximum post spacing.
Fig. 1
6' panel maximum post spacing is 69-3/4"
Step 4:
Mount Posts
1. Mark mounting hole locations and pre-drill a 3/8" [9.5mm]
hole.
2. Insert 3/8" x 3-1/2" [9.5mm x 89mm] Hex Head galvanized
bolts through 3/8" [9.5mm] galvanized washer and post
base plate.
6
HOME base plate a minimum
13
1/2" [12.5mm]
[1771.5mm]
PURE VIEW: Fe
GLASS BALUSTER INSTALLATION
26