Section 7 Commissioning
The configuration data of the boot loader can be retrieved at any time by pressing
the space bar during the waiting time of 2 seconds. The following message will be
displayed:
Enter PIN code: ****
<C>hange, set <T>ime or <P>in, <L>oad config, <S>ave or continue
<B>oot?
The PIN prompt is not displayed during first commissioning, but only after this
safety function has been activated using the terminal program or the display unit.
Configuration data
Select the <C>hange menu item to change the controller configuration data. After
having selected C, the following instruction is displayed.
For each of the following questions, hit <RET> to keep the value in
braces or enter a new value.
The default values for the different configuration items appear in braces. Press the
ENTER key to confirm the displayed value or change the values as required.
IP addresses
The IP addresses of the Ethernet interfaces can be set using the terminal program.
For each on-board Ethernet interface, a prompt that requests the entry in
DDD.DDD.DDD.DDD format is displayed. The address is entered as decimal
number (DDD = 0...255). Leading zeros can be omitted.
For example: 172.16.1.22 <ENTER>
Enter IP address: [172.16.1.22]
An IP address must be assigned to each Ethernet interface in the various subnets.
It is recommended to set an IP address within the range of 172.16.[0 - 15].[0 -
255] for the Control Net.