Before going to any site, please be sure you completely prepared the following items:
1- The installation tools.
2- The test equipment ,materials ,and tools.( for test work only)
3- Site installation drawings.
4- All labels/stickers (hard and soft copy)
5- Frequency plan and system configuration documents.
6- Test procedure and test data sheets .( for test work only)
7- Confirm access to site/station.
8- Check the condition of the vehicle to be used.
9- Make sure you and your staff are in good conditions (physically)
10- Confirm the site/station entrance conditions.
11- Arrive to site/station safely.
Notes:
1- The installation tools (per team) include:
Description
Tap rule 50 M.
Square 150mm x 100 mm.
Scriber
Level A-type 450 mm.
Tester .
Wrench set A-type 6-24 mm
Adjustable wrench 150 mm
Adjustable wrench 250 mm
Socket wrench kit
Screw driver (-) 150
Screw driver (+) NO.3 (150)
Straight shank drill set (3.0 – 13.0 mm)
Concrete drill set (4.8 – 18.0 mm)
Drill bag
Electric drill 6.5 mm (230 V)
Hammer drill 19 mm (230 V)
Point drill 6.4 mm (with holder)
Point drill 6.4 mm
Center punch 125 mm
Hack saw frame
January 2002
Before going to site check list
PASOLINK installation procedure
Quantity
1
1
1
1
1
2
2
2
1
1
1
5
5
2
1
1
1
1
1
2
Need help?
Do you have a question about the PASOLINK and is the answer not in the manual?
Questions and answers